Work Schedule Pembinaan Rumah Dari Awal Hingga Akhir





WORK SCHEDULE

PRELIMINARIES

  • Order Bahan Binaan
  • Susun Atur Tapak
  • Mohon Bekalan Air & Letrik Sementra
  • Setting Out & Side Rail

FABRICATING WORKS

  • Formwork
  • Re Bar

SUB STRUCTURE

  1. 1. EXCAVATION/INSTALLATION/CONCRETING
  • Menggali Tapak Asas
  • Grid Line allignment
  • Memasang Formwork
  • “Lean Concrete 2″””
  • Memasang besi / re-bar
  • Kerja-kerja konkrit tapak asas

 

  1. 2. DISMENTLING WORKS/RE-FILL EARTH
  • Membuka papan formwork
  • Kerja menimbus kembali tanah

 

  1. 3. MEMBINA GROUND BEAM
  • Grid Line allignment/levelling
  • Pasang forwork
  • Pasang besi / re-bar
  • Tie up / support formwork
  • Kerja-kerja Concreting to Grd Beam

 

  1. 4. GRD FLOOR SLAB
  • Mengisi tanah/pasir/hardcore
  • Menghampar Plastic sheet
  • Menghampar BRC
  • Concrete Pouring to Slab

SUPER STRUCTURE

  1. 1. MEMBINA TIANG
  • Grid Line allignment/levelling
  • Pasang besi / re-bar
  • Pasang formwork
  • Checking verticallity and tie-up formwork
  • Concrete Pouring to column
  1. 2. MEMBINA ROOF BEAM
  • Menyedia/menaikkan T-support/staging
  • Pasang roof beam bottom formwork
  • Pasang roof beam side formwork
  • Masukkan tetulang besi/re-bar
  • Tie-up roof beam formwork
  • Concrete Pouring to roof beam
  1. 3. KERJA-KERJA BUMBUNG
  • Pasang wall plate dan kekuda
  • Laying aluminium foil/timber battern
  • Pasang atap genting
  1. 4. KERJA BATA, PLASTER, FRAME PINTU/TINGKAP DAN SILING
  • Pasang Frame Pintu
  • Kerja Mengikat Dinding bata
  • Pasang frame tingkap
  • Kerja-kerja plaster
  • Kerja-Kerja Siling

COLD WATER PLUMBING/SANITARY/SEWERAGE

  • Under ground paip
  • Piping and Sanitary fitting
  • Sewer pipe and septic tank

KERJA-KERJA LETRIK

  • Cable laying
  • Electrical appliance

FINISHING WORKS

  • Floor and Wall tiles
  • Painting
  • Fixing Door/Window leaf

EXTERNAL WORKS

  • Perimeter drain and Turfing